report that the data centre construction market is hot or overheating

On average, what has been the percentage change in construction tender / bid prices

report a more than a 15% average increase in tender / bid prices

expect to see an increase in data centre construction claims / litigation during 2023 relating to cost escalation, inflation and supply chain issues

expect data centre construction costs to continue to rise in 2023

agree delays or challenges in securing power to sites have had a severe impact on data centre delivery

Respondents are more concerned by:

0%

Schedule delays

0%

Material prices

0%

Labour prices

consider the data centre industry to be recession-proof

say that data centre construction has struggled to meet demand over the past 12 months

report that material shortages have caused delays to data centre construction over the past 12 months

To what extent have lead times for key data centre construction materials changed on average

report that an increase of more than 8 weeks in lead times for key data centre construction materials

agree there is a shortage of experienced data centre construction teams

don’t think the data centre sector has a clear, measurable plan to achieve net-zero carbon

are increasingly concerned about the solvency of the data centre supply chain

say construction tender / bid prices have escalated by a higher percentage in 2022 than 2021