Methodology

To produce our data center construction cost index for 2026, data center benchmarking cost data was captured from over 500 live or recent projects across 62 markets. All costs are converted into US dollars. To supplement our construction cost data, we also conducted an online poll of 400 experts working across the data center industry.

Construction cost data is captured under the following key capital cost headings: shell and core, architectural fit-out and finishes, mechanical and electrical fit-out, general contractor preliminaries, general contractor margin, general contractor contingency, and mechanical and electrical equipment. All costs are converted into USD using the average foreign exchange rate between 1 Oct 2025 and 1 Oct 2026.

Exchange rates

We used the average FX rate between 1 October 2025 and 1 October 2026 for the conversions to USD. 2025-2026 continues to experience some significant exchange rate fluctuations between USD and other currencies.

Baseline model assumptions

Benchmarking cost data has been modified to represent a typical air-cooled, build-to-suit hyperscale data center in the average range of 60MW (IT load). Multi-client colocation facilities or enterprise end-user facilities may change the indicated US$/w by up to 15%. Latest available benchmark data from US liquid-cooled data centers indicates an average cost premium of 7-10% when compared to air-cooled data center benchmarks of similar IT load.

Shell and core

Our network of regional offices provided real project benchmark data for actual data center shell and core construction expenses, where available.

Equipment

Actual quoted equipment costs have been applied and factored in as necessary. Additional costs per location are also applied for local sales tax/VAT, import duties and freight where applicable.

Construction labor and materials

The index results incorporate actual construction labor and materials costs from live or recent projects in each market.

Preliminaries/general conditions and general requirements

The index results incorporate actual preliminaries/general conditions and general requirements costs from live or recent projects in each market.

Exclusions

The cost model does not include any client direct costs, land purchase costs, utility works, abnormal groundworks, site works, active IT equipment, fibre cabling to support office fit-outs or professional services fees.

About Turner & Townsend

Turner & Townsend is a global program management company with over 23,000 people in 64 countries.

Working with our clients across real estate, infrastructure, energy and natural resources, we transform together delivering outcomes that improve people’s lives. Working in partnership makes it possible to deliver the world’s most impactful projects and programmes as we turn challenge into opportunity and complexity into success.

Our capabilities include programme, project, cost, asset and commercial management, controls and performance, procurement and supply chain, net zero and digital solutions.

We are majority-owned by CBRE Group, Inc., the world’s largest commercial real estate services and investment firm, with our partners holding a significant minority interest. Turner & Townsend and CBRE work together to provide clients with the premier programme, project and cost management offering in markets around the world.

www.turnerandtownsend.com

© Turner & Townsend Limited. All rights reserved November 2026. This content is for general information purposes only and does not purport to constitute professional advice. We do not make any representation or give any warranty and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this document. It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our express written permission and we accept no liability of whatsoever nature for any use by any other party.

Contents

Follow us

Home
Global overview
Cost trends
Focus on AI data centers
Industry challenges
Future outlook
Methodology
Regional contacts
PDF

© 2026 Turner & Townsend

Privacy Policy

Cookie Policy